| Access to Drinking Water - Well at Soumabougou |
|
| Project Director |
| Tamba Traore |
|
Project Number |
Total Cost (US$) |
Location |
CH04-08 |
$874.46 |
Soumabougou, Mali (Segou) |
|
Project Description

In July 2008, Jigiya president Lamine started construction of a well at Soumabougou. During a 2008 meeting with local officials and advisors, African Sky selected Soumabougo as one of the "10 Schools for 2010" villages. To meet an immediate need in the Soumabougou community, Mali Program Director Tamba Traore developed and managed the construction of a reinforced well on the site of the future elementary school. The African Sky family is eager to further extend our friendship to the people of Soumabougou; we thank the elders, leaders, and people of Soumabougou and Markala who have opened their community and lives to African Sky.
Project Budget | | | |
Items |
Units |
Unit Cost |
Total Cost (CFA) |
Labor |
8 people |
22,500 |
180,000 |
Installation-cement walls |
1 |
69,750 |
69,750 |
Cement (mix) |
8 bags |
3,500 |
28,000 |
Gravel |
12 meters |
|
15,500 |
Sand |
24 meters |
|
32,000 |
Iron - rebar |
|
|
9,750 |
Pulley |
1 |
10,000 |
10,000 |
Pulley support |
1 |
25,000 |
25,000 |
Lid for well |
1 |
20,000 |
20,000 |
Transportation expenses |
|
|
10,000 |
Total African Sky Contribution |
|
|
348,000 CFA* |
*$874.46 |
|
|
|
|


 |
| |
|
|
|